North West Wales (PTC1 and PTNO) – Early Construction Funding and proposed modification to the special conditions of the electricity transmission licence
Related links
- Decision on the Pre-Construction Funding application for the North-West Wales Project in accordance with Special Condition 3.15
- Decision on accelerating onshore electricity transmission investment
Share the page
This consultation sets out our Early Construction Funding (ECF) assessment of the North West Wales project (PTC1 and PTNO) under the Accelerated Strategic Transmission Investment (ASTI) re-opener and our proposed modification to Appendix 1 within Special Condition (SpC) 3.41 'Accelerated strategic transmission investment Re-opener and Price Control Deliverable term (ASTIRt)'.
Respond name
Keren Maschler
Respond telephone
[020 7901 7000](tel:020 7901 7000)
Respond email
RIIOElectricityTransmission@ofgem.gov.uk
Main document
[North West Wales Early Construction Funding and licence statutory consultation [PDF, 417.75KB]
Subsidiary documents
[bp and EnBW NWW response [PDF, 158.08KB]
](https://www.ofgem.gov.uk/sites/default/files/2024-08/bp_and_EnBW_NWW_response.pdf)
[SPT NWW consultation response [PDF, 85.51KB]
](https://www.ofgem.gov.uk/sites/default/files/2024-08/SPT_NWW_consultation_response.pdf)
Related links
- Decision on the Pre-Construction Funding application for the North-West Wales Project in accordance with Special Condition 3.15
- Decision on accelerating onshore electricity transmission investment
Share the page
Pension scheme arrangements for National Grid employees transferring to the Future System Operator (National Energy System Operator or NESO)
Call for input
Yorkshire GREEN project – notice of proposed modifications to the Special Conditions of the electricity transmission licence held by National Grid Electricity Transmission Plc
Consultation