Eastern Green Link 1 Delay Event
Share the page
Outcome of our consultation on the Eastern Green Link 1 (EGL1) Delay Event
Details of outcome
We have completed our assessment of the request for an ASTI ODI Penalty Exemption Period for the EGL1 project. After careful consideration of all relevant submissions, evidence, and regulatory requirements, we have decided to partially approve the request and are awarding 57 days of penalty exemption to EGL1.
Read the full outcome
[Decision on the ASTI ODI Penalty Exemption Period request for Eastern Green Link 1 – EGL1 [PDF, 281.14KB]
](https://www.ofgem.gov.uk/sites/default/files/2025-11/EGL1-PEP-Decision-REDACTED.pdf)[Consultation on the Eastern Green Link 1 (EGL1) Delay Event: responses [ZIP, 1.30MB]
](https://www.ofgem.gov.uk/sites/default/files/2025-11/EGL1-responses-for-publishing.zip)
Original consultation
We are consulting on whether to grant an ASTI ODI Penalty Exemption Period for the Eastern Green Link 1 electricity transmission project. We welcome responses from the Electricity Transmission Owners, other stakeholders and the public.
Consultation documents
[Consultation on the ASTI ODI Penalty Exemption Period request for Eastern Green link 1 (EGL1) [PDF, 270.83KB]