NGET licence modification consultation Large Onshore Transmission Investment

Share the page

At RIIO-ET2 Final Determinations, National Grid Electricity Transmission (NGET) were provided funding in its baseline allowance to deliver substation works at the Melksham substation to connect a customer at the Hinkley Point C nuclear power station, with a delivery date in its electricity transmission licence of 31 December 2024.  

Due to delays completing Hinkley Point C by the developer, NGET has postponed completion of the Melksham substation works until 2028 to align with the revised forecast completion date.

This is a statutory consultation to modify the delivery date in Special Condition 3.13 Large Onshore Transmission Investments Re-opener of NGET’s electricity transmission licence.

Respond name

Shyam Doraiswamy

Respond telephone

02079017000

Respond email

RIIOElectricityTransmission@ofgem.gov.uk

Main document

[Consultation to modify Special Condition 3.13 in NGET's electricity transmission licence: Melksham substation works [PDF, 250.54KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-05/Melksham-Consultation.pdf)

Subsidiary documents

[Notification of proposed licence modification: NGET electricity transmission licence [PDF, 105.03KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-05/Licence-Modification-Notification.pdf)

Share the page