Policy Compass
Electricity transmission

Decision on Connections Reform Package (TM04+)

Share the page

We are publishing a suite of decision and supporting documents to enable connections reform, collectively known as the TM04+ reform package. 

The principal overarching document (main link below) provides an overview of the whole TM04+ reform package, including a summary of responses to our February 14 minded-to consultation. 

In the subsidiary documents you will find:

  • decisions on Code Modifications (CM095, CMP434, CMP435) 
  • decisions on Connections Methodologies (Gate 2 Criteria Methodology, Project Designation Methodology, Connections Network Design Methodology).  
  • decision on the Licence Changes (in response to our February 14 statutory consultation) including Licensee Notice and Appendices' A-C with tracked changes.
  • Impact Assessment 

The Impact Assessment, which underpins our decisions, sets out an appraisal of the potential impacts of these reforms across a spectrum of areas, such as consumers, network build, economic growth and outlines benchmarks of success. 

Altogether, the TMO4+ reform package enables a new electricity connections process that embeds ‘ready’ and ‘needed’ criteria into decision-making when managing requests for electricity connections. 

Main document

[Summary Decision Document: TMO4+ Connections Reform Proposals – Code Modifications, Methodologies and Impact Assessment [PDF, 740.91KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Summary-Decision-Document-TMO4-package.pdf)

[Updates to Connections Methodologies decision [PDF, 94.43KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-05/Updates%20to%20Connections%20Methodologies%20decision.pdf)

Subsidiary documents

[TMO4+ Impact Assessment [PDF, 2.37MB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/TMO4-Impact-Assessment-Decision_0.pdf)

[System Operator (“SO”) – Transmission Owner (“TO”) Code (“STC”) CM095 – Implementing Connections Reform [PDF, 593.79KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/CM095-Final-Decision.pdf)

[Connection and Use of System Code (CUSC) CMP434: Implementing Connections Reform [PDF, 780.82KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/CMP434-Final-Decision.pdf)

[Connection and Use of System Code (CUSC) CMP435: Application of Gate 2 Criteria to existing contracted background [PDF, 671.36KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/CMP435-Final-Decision.pdf)

[Decision: Gate 2 Criteria Methodology [PDF, 424.06KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Gate-2-Criteria-Methodology-Final-Decision.pdf)

[Decision: Project Designation Methodology [PDF, 256.42KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Decision-PDM-updated.pdf)

[Decision: Connections Network Design Methodology [PDF, 352.63KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Connection-Network-Design-Methodology-Final-Decision.pdf)

[Decision on TMO4+ Reform related Modifications to Electricity Licence Conditions [PDF, 470.53KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Decision-on-TMO4-Reform-related-Modifications-to-Electricity-Licence-Conditions.pdf)

[Decision Notice - Modification of the standard conditions of electricity system operator, transmission and distribution licences [PDF, 119.56KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Decision-Notice-modify-the-standard-conditions-of-three-electricity-licences.pdf)

[Annex A - Electricity System Operator Licence - Tracked Changes [PDF, 1.92MB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Annex-A-Electricity-System-Operator-Licence-Proposed-Tracked-Changes.pdf)

[Annex B - Electricity Transmission Consolidated Standard Licence - Tracked Changes [PDF, 1.35MB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Annex-B-Electricity-Transmission-Consolidated-Standard-Licence-Tracked%20Changes.pdf)

[Annex C - Electricity Distribution Standard Licence Conditions - Tracked Changes [PDF, 1.74MB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Annex-C-Electricity-Distribution-Standard-Licence-Conditions-Tracked-Changes.pdf)

[Appendix to Decision Gate 2 Criteria Methodology [PDF, 7.44MB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Appendix-to-Decision-Gate-2-Criteria-Methodology.pdf)

[Appendix to Decision Project Designation Methodology [PDF, 4.11MB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Appendix-to-Decision-Project-Designation-Methodology.pdf)

[Appendix to Decision Connections Network Design Methodology [PDF, 8.07MB]

](https://www.ofgem.gov.uk/sites/default/files/2025-04/Appendix-to-Decision-Connections-Network-Design-Methodology.pdf)

Share the page