Urgency decision for CMP452
Related links
CMP452: Suspension of TNUoS Payments for generators connecting during the 2024/25 charging year
Share the page
Connection and Use of System Code (CUSC) modification proposal CMP452 was raised on 27 February 2025 by Brockwell Energy. The proposed modification seeks to defer Transmission Network Use of System (TNUoS) payments for Generators that connect to the transmission system during 2024/25 until there has been a decision on CMP445. Such deferral would follow a request by a Generator
On 5 March 2025, the proposer requested that the proposal be treated as urgent based on Ofgem's urgency criteria. We have not granted this request. We have set out our reasoning in the attached decision document.
Main document
[Decision on CUSC Modification Panel’s recommendation for CMP452 ‘Suspension of TNUoS Payments for generators connecting during the 2024/25 charging year’ to be treated as an Urgent CUSC Modification Proposal [PDF, 121.61KB]
Related links
CMP452: Suspension of TNUoS Payments for generators connecting during the 2024/25 charging year