Consultation on an Extreme Weather Resilience Medium Sized Investment Project from National Grid Electricity Transmission

Share the page

We are consulting on Ofgem’s assessment of a submission made by National Grid Electricity Transmission (NGET), under the Medium Sized Investment Project (MSIP) reopener. The submission was made in January 2022 under SpC 3.14.6(d) of the MSIP Re-opener licence condition to install surface water flood defences at 33 sites in line with resilience standards set out in the Energy Network Association’s Engineering Technical Report 138.

The MSIP licence condition provides for companies to make reopener submissions during the RIIO-2 price control period for projects that meet certain conditions and cost less than £100m.

Respond name

Graeme Barton

Respond email

graeme.barton@ofgem.gov.uk

Main document

[Consultation on an Extreme Weather Resilience Medium Sized Investment Project from National Grid Electricity Transmission [PDF, 398.64KB]

](https://www.ofgem.gov.uk/sites/default/files/2022-05/Extreme%20Weather%20Resilience%20MSIP%20ConDoc%20final.pdf)

Response documents

[Environment Agency response to an Extreme Weather Resilience Medium Sized Investment Project from NGET [PDF, 220.25KB]

](https://www.ofgem.gov.uk/sites/default/files/2022-08/Environment%20Agency%20response%20to%20an%20Extreme%20Weather%20Resilience%20Medium%20Sized%20Investment%20Project%20from%20NGET.pdf)

[NGESO response to an Extreme Weather Resilience Medium Sized Investment Project from NGET [PDF, 63.47KB]

](https://www.ofgem.gov.uk/sites/default/files/2022-08/NGESO%20response%20to%20an%20Extreme%20Weather%20Resilience%20Medium%20Sized%20Investment%20Project%20from%20NGET.pdf)

[NGET response to an Extreme Weather Resilience Medium Sized Investment Project from NGET [PDF, 412.79KB]

](https://www.ofgem.gov.uk/sites/default/files/2022-08/NGET%20response%20to%20an%20Extreme%20Weather%20Resilience%20Medium%20Sized%20Investment%20Project%20from%20NGET.pdf)

[NGET response to an Extreme Weather Resilience Medium Sized Investment Project from NGET - Flood Inflation Exposure [XLSX, 129.98KB]

](https://www.ofgem.gov.uk/sites/default/files/2022-08/NGET%20response%20to%20an%20Extreme%20Weather%20Resilience%20Medium%20Sized%20Investment%20Project%20from%20NGET%20-%20Flood%20Inflation%20Exposure.xlsx)

[SSENT response to an Extreme Weather Resilience Medium Sized Investment Project from NGET [PDF, 262.44KB]

](https://www.ofgem.gov.uk/sites/default/files/2022-08/SSENT%20response%20to%20an%20Extreme%20Weather%20Resilience%20Medium%20Sized%20Investment%20Project%20from%20NGET.pdf)

[Joint Letter from NGET/SHET/SPT on RIIO-T2 Opex Escalator Uncertainty Mechanism [PDF, 312.91KB]

](https://www.ofgem.gov.uk/sites/default/files/2023-04/Opex%20Escalator_Letter_Ofgem_010323_FINAL.pdf)

Share the page

Consultation on an Extreme Weather Resilience Medium Sized Investment Project from National Grid Electricity Transmission