Policy Compass
Energy network price controls

Consultation: 5 SP Transmission's 2023 MSIP applications

Share the page

The decision for this consultation was published on 20 September 2023.

As part of the RIIO-2 price control, electricity transmission networks have the Medium Sized Investment Project (MSIP) re-opener for projects that meet certain conditions and cost less than £100m. In the January 2023 reopener window, SP Transmission (SPT) submitted eight applications, of which five are initial needs case submissions and the remaining three are full applications. This document summarises our assessment of the five initial needs case submissions as listed below. We will separately consult on our assessment of the full applications at a later date.     

  • Kincardine North 400kV Substation ​
  • Kincardine - Wishaw 400kV Reinforcement
  • XH and XJ Routes Overhead Line Uprating Works
  • Glenglass 132kV Substation
  • Enoch Hill Collector Substation and Associated 132kV Circuit

Respond name

Eliska Antosova

Respond telephone

[020 7901 7176](tel:020 7901 7176)

Respond email

Eliska.Antosova@ofgem.gov.uk

Main document

[Informal consultation on the assessment of five 2023 Medium Sized Investment Project initial needs case submissions from SP Transmission [PDF, 456.31KB]

](https://www.ofgem.gov.uk/sites/default/files/2023-06/ConDoc_SPT_MSIP_2023_Initial_Needs_Case_FINAL.pdf)

Response documents

[SPT response to SPT RIIO-2 MSIP Re-opener Consultation [PDF, 85.02KB]

](https://www.ofgem.gov.uk/sites/default/files/2023-08/SPT%20response%20to%20SPT%20RIIO-2%20MSIP%20Re-opener%20Consultation.pdf)