Consultation on Timelines and Incentives changes for the Third Cap and Floor Window for Interconnectors

Policy Consultation & Statutory Consultation: Pre-Operational Force Majeure event in the Third Window for Electricity Interconnectors

Share the page

A decision for this consultation was published on Tuesday 14 November 2023.

This consultation sets out our proposed new approach to the timelines and incentives framework to be applied to the Third Cap and Floor Window for Electricity Interconnectors. To protect consumers from undue delays and maintain the risk-reward balance between consumers and developers, our changes are centred around the treatment of interconnector project delivery delays.

We are seeking views on our proposals:

  • To introduce a modified approach to the Regime Start Date. This modified Regime Start replaces the Connection Date term introduced in our Application Guidance for the Third Cap and Floor Window for Electricity Interconnectors
  • To introduce Payback Mechanism for Delays 
  • To introduce the modified Backstop Date (including interactions with the Payback Mechanism for Delays) and
  • The Reasonable Delay Event.

Separately we are in parallel consulting on the below, which form part of the wider timelines and incentives framework applied to the Third Cap and Floor Window for Electricity Interconnectors:

The Minded-to Policy Decision document: Pre-Operational Force Majeure requests made in the Third Cap and Floor Window for Interconnectors around pre-FPA decision.

The new standard condition (SLC) 26B: Pre-Operational Force Majeure requests made in the Third Cap and Floor Window for Interconnectors around post-FPA decision.

Please send responses by 31st March 2023 to: Cap.Floor@ofgem.gov.uk

Respond name

Susanna Onyemauwa

Respond email

Cap.Floor@ofgem.gov.uk

Main document

[Cover letter: Consultation on our proposed approach to project delivery delays as part of the timelines and incentives framework applied to the Third Window [PDF, 101.98KB]

](https://www.ofgem.gov.uk/sites/default/files/2023-02/Consultation%20cover_20231677095186287.pdf)

Subsidiary documents

[Consultation on Timelines and Incentives for W3 [PDF, 683.12KB]

](https://www.ofgem.gov.uk/sites/default/files/2023-02/Timelines_RDE%20consultation_20231677095279056_0.pdf)

Response documents

[Response by MaresConnect [PDF, 423.81KB]

](https://www.ofgem.gov.uk/sites/default/files/2023-11/MaresConnect_Response_Delay%20and%20Incentives.pdf)

[Response by Transmission Investment [PDF, 204.85KB]

](https://www.ofgem.gov.uk/sites/default/files/2023-11/TransmissionInvestment_Response_timelines_incentives.pdf)

[Response by NU-Link [PDF, 231.76KB]

](https://www.ofgem.gov.uk/sites/default/files/2023-11/NU-Link_Response_Third%20Cap%20and%20Floor%20Window_March%2023.pdf)

Policy Consultation & Statutory Consultation: Pre-Operational Force Majeure event in the Third Window for Electricity Interconnectors

Share the page