Provisional order issued to Maxen Power over matters relating to energy theft.

Provisional order

We issued a provisional order for Maxen Power Supply Limited on 12 September 2025. It requires them to reinstate records, a new audit to be commissioned and a report provided to us. They will also need a remedial plan to achieve ongoing compliance. Until these issues are resolved, a sales ban has been imposed.

Enforcement description

The Provisional Order requires Maxen Power to complete a number of actions by specified deadlines, including:

  • reinstate records within its Customer Records Management (“CRM”) system.
  • upon the completion of the above requirement, commission an independent audit under SLC 5B from an auditor with forensic accounting capabilities. 
  • provide the Authority with the independent audit report arising as result of SLC 5B.
  • provide the Authority with a detailed remedial plan relating to the calculation, application and communication of all fees detailing how Maxen Power will achieve ongoing compliance with its obligations under the relevant SLCs.
  • be subject to a sales ban and non-essential payments ban until the Authority is satisfied the conditions in the Provisional Order have been met and in accordance with the requirements set out within the relevant SLCs.

Documents

[Maxen Power Supply Ltd: Provisional Order [PDF, 145.83KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-09/20250912%20-%20PO2.%20Provisional%20Order%20-%20Maxen%20Power%20Supply%20Limited.pdf)[Maxen Power Supply Ltd Notice of Reasons [PDF, 181.64KB]

](https://www.ofgem.gov.uk/sites/default/files/2025-09/20250912%20-%20PO1.%20Notice%20of%20Reasons%20-%20Maxen%20Power%20Supply%20Limited%20%28pub%29.pdf)

Maxen Power Supply Limited: enforcement investigation

Share the page