Policy Compass
Gas interconnectors

Decision on the proposed Interconnection Agreement and Pressure Services Charging Agreement between Interconnector Limited and National Grid Gas

Share the page

On 24 May 2022, an Interconnection Agreement and Pressure Service Charging Agreement between Interconnector Limited and National Grid Gas was submitted to the Authority for approval in accordance with Standard Licence Condition 3 of the Gas Interconnector Licence - 'Compliance with bilateral agreements'.

This letter sets out our decision to approve the proposed agreements on the basis that its contents have been agreed by both parties.

Main document

[Interconnection and Pressure Services Charging Agreements Decision Letter June 2022 [PDF, 82.76KB]

](https://www.ofgem.gov.uk/sites/default/files/2022-06/Interconnection%20and%20Pressure%20Service%20Charging%20Agreements%20INT%20NGG%20Decision%20Letter%20June%202022.pdf)